Borealis Provides Fiscal 2027 Production and Operating Guidance - TradingView
AI desk brief
Borealis guided FY2027 gold output at 15,250-19,250 oz from its Nevada Borealis mine, with total material mined of about 6.0 million tons and an average strip ratio near 2.4:1. Management said most production should come from Deep Ore Flats, with East Ridge and Freedom Flats as supplements.
The company is also adding run-of-mine heap leaching alongside crushed stacking to relieve crusher bottlenecks, targeting 717,960 tons of crushed material and 1,055,850 tons of ROM stacking. Borealis plans engineering and permitting for a new heap-leach pad with 8-12 million tons of capacity and ADR upgrades to lift throughput and support future production growth.
Sources used
- S1 TradingView via Google News — Borealis Provides Fiscal 2027 Production and Operating Guidance - TradingView