Vizsla delays first silver at Panuco by a year

Mining.com Tier 2 2026-11-19 14:07 UTC 📖 1 min brief Neutral
Silver

AI desk brief

Vizsla Silver delayed first silver at Mexico’s Panuco project by one year to second-half 2028 as it prepares a phased return after the abduction and killing of 10 workers. Engineering is roughly halfway complete and 85% of plant equipment is ordered, but federal approvals and a production decision remain outstanding. The November 2025 feasibility study projected 94.7 million oz of payable silver and 776,000 oz of gold over 9.4 years, with $238.7 million initial capital; estimates exclude the revised schedule, potential cost increases and financing costs. The delay could defer future supply, but no material near-term bullion effect is established.